Inception date: 29 Jun 2016 | Removal date: open ended
Still in force

Trade finance

The project value is 140.69 million CHF (144 million USD) and it finances the conversion of an existing gas fired steam turbine (no. 3) from 210MW into a combined cycle power plant with 400MW by General Electric, Baden.

The maturity of the loan will be longer or equal to two years. The SERV differentiates between nine categories of fiancial support. The present project is a buyer credit insurance (category B).

AFFECTED COUNTRIES

MAP
TABLE
EXPORT

AFFECTED SECTORS AND PRODUCTS

432 Pumps, compressors, hydraulic & pneumatic power engines; parts
8412 Other engines and motors.
841280 Other